By Noah Rothman
Thursday,
March 14, 2024
Shrewd
outside observers of the progressive left’s most desired policy reforms can’t
help but notice that their wildly inflated price tags rarely correlate with
outcomes. Indeed, what the money is supposed to achieve is often given short
shrift — the expenditure speaks for itself. Skeptics can be forgiven for
concluding that the spending is the whole point.
In
Joe Biden’s era, the “American Rescue Plan” with its $1.9 trillion
Covid-relief, was hailed as “the biggest investment” in Democratic policy priorities
since 1945 — the “largest-ever one-time federal investment” to objects of
progressive desire. What it was designed to do — deliver America from the
pandemic — was beside the point. Biden’s infrastructure bill, which was
whittled down to about $1 trillion from the White House’s preferred $2.3
trillion ask, was hailed as “the largest American jobs investment since World War II.”
The progressive wish-list items that failed in Congress are touted for their “bigness,” not in the scope of their objectives but in the
sums they would appropriate. Conversely, proposed reforms that the left sees as
failing to meet the measure of the moment are condemned because their price
tags should be, in Alexandria Ocasio-Cortez’s words, “way
higher.”
By
this metric, progressives should and probably do regard California’s
frustrating efforts to construct a high-speed-rail network across the state as
a wild success. “The project has spent $9.8 billion so far,” CNBC reported in the spring of last year. “But 15
years later, there is not a single mile of track laid, and executives involved
say there isn’t enough money to finish the project.” This week, the stalled
effort to develop a train that travels between Los Angeles and San Francisco at
the desired pace encountered another obstacle: the coffers had once again run
dry.
During
a hearing this week before the California State Senate’s Transportation
Committee on the High-Speed Rail Authority’s business plan, the project’s CEO,
Brian Kelly, confessed that the program was all but broke with a meager $28
billion left in the bank. Engineering a stretch of rail line between Merced and
Bakersfield was expected to cost between $32 and $35 billion, which would allow
it to begin operating within the next six to nine years.
“Project
leaders estimate it will still need an additional $100 billion to finish what
voters were originally pitched in 2008,” one California-based media outlet reported. But California
alone may not have to foot the entire bill. “Kelly told lawmakers he’s
encouraged by an ongoing discussion with the Biden administration on
establishing a railroad trust fund, and recent funds it received through the
Bipartisan Infrastructure Act,” that report continued. “Kelly said the project
needs a strong, long-term federal partner.”
The
total estimated cost of this project has ballooned since it was approved by
lawmakers in Sacramento during the Bush administration. All told, the rail
network is expected to cost a staggering $128 billion. But the project has been
plagued by a version of Zeno’s paradox. The more that is appropriated for it,
the more money it needs. In 2022, the California High-Speed Rail Authority
revealed that the total cost of the project had jumped “nearly 22% uptick from
the previous figure of $105 billion,” Construction Drive reporters observed. That’s “a
far cry from the $33 billion cost voters approved in 2008.”
And
even in the distant future, when the project is expected to be completed, it
will still require vast amounts of funding to maintain operations. Its CEO is
vexed by Sacramento’s failure to conceive of his rail line as a gaping maw into
which taxpayer funds must be shoveled in perpetuity. “Every country around the
world that has built high-speed rail has dedicated billions of dollars over
several decades to see it through,” he complained. “We don’t have one penny of state support
for this project identified after 2030.”
All
this for a project that the bureaucracy Kelly heads estimates will generate an
annual ridership of roughly 31.3 million riders by 2040. That’s a decline from
pre-pandemic estimates — a decline that calls into question the utility of the
whole enterprise. “If the high-speed rail system averaged 11.5 million people a
year paying $86 for a ticket,” a SiliconValley.com analysis posited, it would take
roughly 108 years for the project to even begin paying for itself. And that
assumes a ridership that vastly eclipses what California’s Pacific Surfliner
rail currently attracts. “It would take more than 1.25 billion people paying
that $86 a ticket for the estimated $107.6 billion high-speed rail system to
break even,” the analysis continued. “That is the equivalent of 32 times the
population of California in 2023.”
We’re
left to conclude that this boondoggle, which fills no discernible gap in
California’s infrastructural needs and costs the equivalent of what it would
take to build a new fleet of nuclear-missile submarines, is desirable
only because it is desired. The left does love their trains. And that seems to
be the whole value proposition here. That, and the fact that a ton of money is
being spent. What more can you ask of California?
No comments:
Post a Comment